I'm very new to the site and it seems very helpful.
I'm a 9001/14001/18001 and 27001 assessor in the UK with limited BRC knowledge but I've been asked to help someone out until they get someone in place and trained.
I'm planning to do my BRC training but I'm hoping someone can help with one question?
My client does not have BRC but has recently had an audit by a client. One of the non conformances related to the fact that the process flow chart had no CCPs identified. When reviewing them some time ago, the client had thought that there were no ccps and produced only a stage flow diagram.
My client orders goods, receives and warehouses them at ambient temp and arranges delivery (own and third party transport).
Auditor has mentioned ccps including: date checks, damaged/blown stock at delivery,storage and dispatch of product.
Can anyone throw light on this?
many thanks
@ISOkirst