Hi all,

 

I'm looking for a sample procedure for returning equipment into process after repairs etc.

 

Thanks

Tracey



redfox

    Grade - SIFSQN

  • IFSQN Senior
  • 481 posts
  • 163 thanks
24
Excellent

  • Philippines
    Philippines

Posted 10 April 2018 - 07:21 AM

Hello,

 

Just follow what you are doing now, but then don't forget to include what the standard requirements to be followed. Ex: it must be verified by an authorized person that it is functional and can do its intended use, no missing parts (if it is done inside prod area). Then it must received by the end user from the maintenance department also must be verified.

 

regards,

redfox



FurFarmandFork

    Food Safety Consultant, Production Supervisor

  • IFSQN Fellow
  • 1,264 posts
  • 590 thanks
206
Excellent

  • United States
    United States
  • Gender:Male
  • Location:Oregon, USA

Posted 10 April 2018 - 02:46 PM

Simple: maintenance signs off repair is completed. Sanitation signs off it is clean and ready for use.

 

Extra: Maintenance signs off that repair is completed, sanitation signs off it is clean and ready for use, maintenance observes the equipment once more after installation to verify no broken/missing parts or poor assembly.


Austin Bouck
Owner/Consultant at Fur, Farm, and Fork.
Consulting for companies needing effective, lean food safety systems and solutions.

Subscribe to the blog at furfarmandfork.com for food safety research, insights, and analysis.

Scampi

    Fellow

  • IFSQN Fellow
  • 5,444 posts
  • 1507 thanks
1,524
Excellent

  • Canada
    Canada
  • Gender:Not Telling

Posted 10 April 2018 - 02:51 PM

don't forget to ensure the pre op is completed prior to use as well


Please stop referring to me as Sir/sirs


MsMars

    Grade - PIFSQN

  • IFSQN Principal
  • 606 posts
  • 194 thanks
151
Excellent

  • United States
    United States
  • Gender:Female

Posted 10 April 2018 - 04:01 PM

One more additional item: signoff that all tools have been removed. 

We've combined this all into one form... description of problem, equipment involved, circle Y/N for tools removed, area cleaned/sanitized, and pre-op inspection completed, then signoff by supervisor(s) and/or maintenance.



Cravin' Cajun?

    Grade - MIFSQN

  • IFSQN Member
  • 51 posts
  • 30 thanks
0
Neutral

  • United States
    United States
  • Gender:Female
  • Location:Louisiana
  • Interests:Food Safety, HACCP, BRC, Spices

Posted 11 April 2018 - 09:48 PM

My company uses the attached "Equipment Re-Instatement Checklist" for this purpose...hope it helps!