Could anybody please help me? I work at a packaging plant and need to write line clearance procedure and check sheet, but having some difficulties with it, Thanks in advance!!!
Gilang
Posted 15 October 2012 - 10:40 AM
Posted 22 October 2012 - 07:00 PM
Line clearance procedure is to prevent mixing product...a very serious issue in the food industry. Often considered a CCP line clearance usually involves clearing the machine and work area of all materials and documents from the current order before moving onto the next order. The procedure is usually carried out against a documented checklist which is signed off by the operator and is often double checked and countersigned by a second operator. On reel-fed packaging often materials from the old and new order have to be joined to save re-threading the machine - in which case the taped join should be retained as evidence the line clearance was completed effectively. I have some documents i will dig out for you.
Regards,
Simon
Get FREE bitesize education with IFSQN webinar recordings.
Download this handy excel for desktop access to over 180 Food Safety Friday's webinar recordings.
https://www.ifsqn.com/fsf/Free%20Food%20Safety%20Videos.xlsx
Check out IFSQN’s extensive library of FREE food safety videos
https://www.ifsqn.com/food_safety_videos.html
Thanked by 1 Member:
|
|
Posted 25 October 2012 - 01:59 AM
Line clearance procedure is to prevent mixing product...a very serious issue in the food industry. Often considered a CCP line clearance usually involves clearing the machine and work area of all materials and documents from the current order before moving onto the next order. The procedure is usually carried out against a documented checklist which is signed off by the operator and is often double checked and countersigned by a second operator. On reel-fed packaging often materials from the old and new order have to be joined to save re-threading the machine - in which case the taped join should be retained as evidence the line clearance was completed effectively. I have some documents i will dig out for you.
Regards,
Simon
Posted 25 October 2012 - 03:57 AM
Here is an example of a Production change-over record - maybe this will help putting you on the right track to put something toether
QCAPPROVAL FOR CHANGE OVER ON PRODUCTION LINES
PRODUCTPACKAGING
QC SIGN
LINE MANAGER SIGN
ACTION TAKEN
1. CARTONPosted 25 October 2012 - 08:39 AM
The attached would be stored with the production order documents and samples, which are also reviewed by management with action taken on any problems or comments made by operators. If the line clearance was not completed properly then product withdrawal would be initiated.
Regards,
Simon
Get FREE bitesize education with IFSQN webinar recordings.
Download this handy excel for desktop access to over 180 Food Safety Friday's webinar recordings.
https://www.ifsqn.com/fsf/Free%20Food%20Safety%20Videos.xlsx
Check out IFSQN’s extensive library of FREE food safety videos
https://www.ifsqn.com/food_safety_videos.html
Thanked by 3 Members:
|
|
Posted 29 October 2012 - 02:10 AM
The attached would be stored with the production order documents and samples, which are also reviewed by management with action taken on any problems or comments made by operators. If the line clearance was not completed properly then product withdrawal would be initiated.