Hello all,

 

We have existing production plant and will install new parallel machine for new production line in same plant. Raw are from same sources but hopely finished product will be store in different tank. In this situation, do I need to prepare Change Management Form and announcement to our suppliers and customers?



pHruit

    Grade - FIFSQN

  • IFSQN Fellow
  • 2,072 posts
  • 849 thanks
537
Excellent

  • United Kingdom
    United Kingdom
  • Gender:Male
  • Interests:Composing/listening to classical music, electronics, mountain biking, science, sarcasm

Posted 18 April 2019 - 10:46 AM

Not sure why you'd need to tell your suppliers?
But yes, I'd expect that this should go through your change management procedure.

You may need to let customers know, depending on the specific agreements/approvals that you have in place with them. For example, if they've approved you as a supplier based on an audit of a specific line and you will be changing to a different line then yes, you will almost certainly need to advise them.
Similarly, many of them may have contractual requirements or general warranties that stipulate that they must be informed in advance of any change.



Thanked by 1 Member:

Charles.C

    Grade - FIFSQN

  • IFSQN Moderator
  • 20,542 posts
  • 5665 thanks
1,544
Excellent

  • Earth
    Earth
  • Gender:Male
  • Interests:SF
    TV
    Movies

Posted 18 April 2019 - 10:57 AM

Hi Su Lei,

 

Any significance just might relate to what yr business actually is.


Kind Regards,

 

Charles.C


Thanked by 1 Member:

SQFconsultant

    SQFconsultant

  • IFSQN Fellow
  • 4,662 posts
  • 1139 thanks
1,132
Excellent

  • United States
    United States
  • Gender:Male
  • Interests:Just when I thought I was out - They pulled me back in!!!

Posted 18 April 2019 - 02:04 PM

My clients issue change alerts to both customers and suppliers as deemed needed - as in who is involved.  So, they don't issue them to every single supplier and customer.   If they add a line that is making a different type of item most issue notices to ALL suppliers and customers in an effort to increase business from those that would be interested in what they will be doing on the next line/section, etc.


All the Best,

 

All Rights Reserved,

Without Prejudice,

Glenn Oster.

Glenn Oster Consulting, LLC -

SQF System Development | Internal Auditor Training | eConsultant

Martha's Vineyard Island, MA - Restored Republic

http://www.GCEMVI.XYZ

http://www.GlennOster.com

 


Thanked by 1 Member:

Gerard H.

    Grade - SIFSQN

  • IFSQN Senior
  • 411 posts
  • 131 thanks
44
Excellent

  • France
    France
  • Gender:Male

Posted 18 April 2019 - 07:12 PM

Dear Su Lei,

If your change management procedure works well, normally it will give you the answer on what to do.

Kind regards,

Gerard Heerkens