Posted 14 June 2022 - 03:52 PM

Hello experts!

As many are aware, everyone has an opinion of every subject with food safety and auditing. I need some guidance on traceability reconciliation. Is there a number (95% ?) than is ideal when performing a traceability / recall exercise.

I currently work in a fresh produce processing / distribution operation and accounting for precisely 100% of anything is next to impossible.



SQFconsultant

    SQFconsultant

  • IFSQN Fellow
  • 4,662 posts
  • 1139 thanks
1,132
Excellent

  • United States
    United States
  • Gender:Male
  • Interests:Just when I thought I was out - They pulled me back in!!!

Posted 14 June 2022 - 04:42 PM

In a situation like that it would be better to recall over 100% - because the target is 100%.


All the Best,

 

All Rights Reserved,

Without Prejudice,

Glenn Oster.

Glenn Oster Consulting, LLC -

SQF System Development | Internal Auditor Training | eConsultant

Martha's Vineyard Island, MA - Restored Republic

http://www.GCEMVI.XYZ

http://www.GlennOster.com

 


kingstudruler1

    Grade - PIFSQN

  • IFSQN Principal
  • 852 posts
  • 291 thanks
257
Excellent

  • United States
    United States

Posted 14 June 2022 - 05:26 PM

there used to be some auditing standards (maybe there still is) that stated ranges.   something like 98 - 102% as I recall.  

The goal should be 100%.   I think you need to be able to justify or defend the standard that you determine.   In different operations, there are legitimate reasons for not being able to achieve 100% recovery (water loss, spillage, scrap, etc).  What you don't want to do is to set a standard such as 95% and have no idea/justification/explanation/data as to how you determined that standard.  


eb2fee_785dceddab034fa1a30dd80c7e21f1d7~

    Twofishfs@gmail.com

 


Scampi

    Fellow

  • IFSQN Fellow
  • 5,486 posts
  • 1511 thanks
1,550
Excellent

  • Canada
    Canada
  • Gender:Not Telling

Posted 14 June 2022 - 06:04 PM

The best solution is to follow Glenn's advice---once you've done a full trace exercise a couple of times you'll know what you're actually capable of achieving and adjust your program accordingly

 

For example, we have in process waste containers-however when we have a really bad run (item specific) the waste containers may overflow into the drain and we have no idea how much we've lost (ag commodities too many variables) so perhaps today's trace yields me 99%, tomorrow may only be 85% 

 

Once you have performed a couple of trace, you'll have actual data into where you are losing product (does your product shrink in the warehouse, does it absorb moisture, how often are FG verified for quantity/weight etc.) Then you can adjust your procedure/program with an explanation of where the variance to 100% is coming from 