Posted 18 December 2020 - 11:48 AM

Hello everyone, we want to construct a mini-workshop (that would contain some spare parts and tools for mechanical work), and some mechanical work except for cutting, grinding and other related work to be done there, inside production area of our facility, which is a highly sensitive area. What does FSSC22000 recommends about this? Regards,

M. Anwer Khattak



jdpaul

    Grade - SIFSQN

  • IFSQN Senior
  • 256 posts
  • 221 thanks
53
Excellent

  • United States
    United States

Posted 18 December 2020 - 02:19 PM

This would be in the first few sections of the ISO/TS 22002-1:2009 Prerequisite programmes on food safety. If you have the tech. standard look at sections 4 and 5.

 

It doesn't say you can't do it but you need to give consideration to the layout of the mini-workshop and its interaction with parts of the food processing areas and how potential sources of contamination could occur. Essentially you need a documented risk assessment. I would do an (FMEA) for all the activities in the shop and the failures for each step that could cause contamination and how you would control those. Routinely review this to ensure nothing has changed


Edited by jdpaul, 18 December 2020 - 02:20 PM.

  • olenazh likes this

Thanked by 1 Member:
Anwer Khattak

Charles.C

    Grade - FIFSQN

  • IFSQN Moderator
  • 20,542 posts
  • 5665 thanks
1,545
Excellent

  • Earth
    Earth
  • Gender:Male
  • Interests:SF
    TV
    Movies

Posted 19 December 2020 - 07:00 AM

Hello everyone, we want to construct a mini-workshop (that would contain some spare parts and tools for mechanical work), and some mechanical work except for cutting, grinding and other related work to be done there, inside production area of our facility, which is a highly sensitive area. What does FSSC22000 recommends about this? Regards,

M. Anwer Khattak

 

Hi Anwer Khattak,

 

You can find some analogous queries to this in previous threads for other Standards. Mostly pessimistic towards subsequent findings.

 

From an auditorial viewpoint I predict that such an installation is, operationally, likely to create a bucket load of headaches from various directions, eg contamination, worker flow patterns etc etc .


Kind Regards,

 

Charles.C


Thanked by 1 Member:
Anwer Khattak

Ryan M.

    Grade - FIFSQN

  • IFSQN Fellow
  • 1,329 posts
  • 479 thanks
290
Excellent

  • United States
    United States
  • Gender:Male
  • Location:Birmingham, AL
  • Interests:Reading, crosswords, passionate discussions, laughing at US politics.

Posted 19 December 2020 - 01:44 PM

I would ask / wonder why it is needed?  What is the purpose?  I say this because in my previous facility we would rebuild a lot of valves during equipment downtime for PM's.  We had a mobile work table built for this purpose and just wheeled it into the area where we were working on the valves.  Could this be an option?  Would it suffice for what is needed?

 

As Charles mentioned, there's no specific limitation, but it opens a lot of questions and potential headaches.



Anwer Khattak

    Grade - Active

  • IFSQN Active
  • 16 posts
  • 6 thanks
1
Neutral

  • Pakistan
    Pakistan

Posted 21 December 2020 - 03:22 AM

I would ask / wonder why it is needed?  What is the purpose?  I say this because in my previous facility we would rebuild a lot of valves during equipment downtime for PM's.  We had a mobile work table built for this purpose and just wheeled it into the area where we were working on the valves.  Could this be an option?  Would it suffice for what is needed?

 

As Charles mentioned, there's no specific limitation, but it opens a lot of questions and potential headaches.

Hi Ryan,

As we are working in a highly controlled and sensitive area, we have certain entry and exit protocols for personnel and for all the tools etc that are supposed to enter the area, so the mini workshop is needed to reduce time needed to do the work and for the personnel to go out and then again come in to the area. The mini worshop is also supposed to keep some stock of spare parts that may be needed.

 

Regards,

M. Anwer Khattak