BRC 8 - 5.4.4: How to meet the requirement for Mass Balance Tests?

Started by , May 29 2019 03:30 AM
4 Replies

According to  BRC version 8

 

5.4.4           " The site shall undertake documented mass balance tests at a frequency to meet the particular scheme requirements or at least every 6 months in the absence of a scheme-specific requirement.The site shall undertake documented mass balance tests at a frequency to meet the particular scheme requirements or at least every 6 months in the absence of a scheme-specific requirement." 

 

 

can someone explain to us what it means and how to meet this requirement.

 

 

Thanks

Share this Topic
Topics you might be interested in
Organic Audit: Mass balance audits What is the requirement for damaged ingredient bags in dry storage area? Liner Bag Requirement for Packaging Plastic Food Packages RSPO Mass balance clarification Does anyone use a specialized software to input data from lab tests?
[Ad]

This section applies if you are making any specific product claims - e.g. Organic, Fairtrade, non-GMO etc.

For some of these (e.g. Organic) there is separate certification required, and the relevant certification schemes may mandate a minimum frequency for traceability and mass balance tests.

This BRC clause requires that in the absence of any requirements from a specific other certification scheme, you do your internal test at least once every 6 month.

 

Have you got a copy of the BRC Issue 8 Interpretation Guidelines? If not then this is worth obtaining - it's free if you're already on the BRC Participate scheme, or £125 from the BRC Bookshop here if not. If it's your first time doing BRC then I believe this will be a very sensible purchase for you.

1 Thank

This section applies if you are making any specific product claims - e.g. Organic, Fairtrade, non-GMO etc.

For some of these (e.g. Organic) there is separate certification required, and the relevant certification schemes may mandate a minimum frequency for traceability and mass balance tests.

This BRC clause requires that in the absence of any requirements from a specific other certification scheme, you do your internal test at least once every 6 month.

 

Have you got a copy of the BRC Issue 8 Interpretation Guidelines? If not then this is worth obtaining - it's free if you're already on the BRC Participate scheme, or £125 from the BRC Bookshop here if not. If it's your first time doing BRC then I believe this will be a very sensible purchase for you.

So, if I understand correctly I must perform a traceability test + material balance at least once every 6 months in case of allegation.

The short answer is yes.
The longer answer is that it could depend on which specific claim(s) you're making and any other requirements relating to it - for example, if you're labelling a product as organic and your organic certifier stipulates a requirement to do a mass balance / trace every 3 months then this would override the BRC requirement. (I'm not readily aware of any schemes that do have such a requirement, so just an illustration).

1 Thank

The short answer is yes.
The longer answer is that it could depend on which specific claim(s) you're making and any other requirements relating to it - for example, if you're labelling a product as organic and your organic certifier stipulates a requirement to do a mass balance / trace every 3 months then this would override the BRC requirement. (I'm not readily aware of any schemes that do have such a requirement, so just an illustration).

 

Right

 

Thanks


Similar Discussion Topics
Organic Audit: Mass balance audits What is the requirement for damaged ingredient bags in dry storage area? Liner Bag Requirement for Packaging Plastic Food Packages RSPO Mass balance clarification Does anyone use a specialized software to input data from lab tests? Getting a company to meet requirements, how do you do it? Requirement of Traded Goods-BRCGS Issue 9 Are there any hygienic design requirement for the dosing and control of MAP gases Toilet Requirement per number of employees Facility specification of cold room as per guideline of EU requirement