SQF Management Review Hazard and risk management system;

Started by , Jul 06 2019 10:14 PM
5 Replies

Please provide some examples of what should be reviewed to meet the SQF Management Review section that covers review of the hazard and risk management system requirement.

Share this Topic
Topics you might be interested in
Food Safety Culture in a Low Risk Product Facility (Wine) Flow Charts and Hazard Analysis HACCP plan for chocolate and risk area decision tree Environmental Monitoring Risk Assessment Is a scanning system required as part of the sqf certification?
[Ad]

Please provide some examples of what should be reviewed to meet the SQF Management Review section that covers review of the hazard and risk management system requirement.

 

Please state which Clause you are referring to.

2.1.3 Management Review (Mandatory)
What the SQF Code says
2.1.3.1 The senior site management shall be responsible for reviewing the SQF System and documenting the
review procedure. Reviews shall include:
i. The policy manual;
ii. Internal and external audit findings;
iii. Corrective actions and their investigations and resolution;
iv. Customer complaints and their resolution and investigation;
v. Hazard and risk management system; and
vi. Follow-up action items from previous management review.

2.1.3 Management Review (Mandatory)
What the SQF Code says
2.1.3.1 The senior site management shall be responsible for reviewing the SQF System and documenting the
review procedure. Reviews shall include:
i. The policy manual;
ii. Internal and external audit findings;
iii. Corrective actions and their investigations and resolution;
iv. Customer complaints and their resolution and investigation;
v. Hazard and risk management system; and
vi. Follow-up action items from previous management review.

 

Hi SpeedySnacks.

 

Thks for info.

 

Just for initial background here is the Guidance material -
 

 

2.1.3  Implementation Guidance

 

What does it mean?

This element is closely linked to 2.1.2 and is one of the tangible actions which demonstrate management commitment and involvement.

The supplier must review their SQF System when any changes occur that impact food safety.  This may include changes to product formulations, raw or packaging materials, processing or packaging equipment or changes to personnel.  The SQF practitioner is responsible for managing such changes, but senior management is responsible for authorizing and approving these changes.

The SQF System shall be reviewed and update changes communicated (at a minimum) monthly to senior site management as part of the review of all operational activities.  Additionally, a full review of the SQF System must be completed annually by senior management.

 

What do I have to do?

This element is mandatory.  This (at a minimum) annual review, including monthly updates for site management, shall include the policies outlined in company’s policy statement, findings from the regularly scheduled internal and external audits, customer complaints, test records, deviation reports and outcomes of corrective actions.

A procedure documenting how the review of SQF System is conducted shall be included in the food safety manual.  The review must be conducted by senior management with the objective of ensuring the continued integrity of the food safety management system.  

The review shall measure the effectiveness of the SQF System against the food safety objectives established by senior management and the effectiveness of corrective actions taken in response to deficiencies in the System.  The focus shall also be on the effectiveness of pre-requisite programs and the ongoing accuracy and validation of the Food Safety Plan (s). 

All reviews and major changes to the SQF System shall be recorded by the SQF practitioner, including the reasons for any changes and the actions taken as a result of changes or reviews.

Major changes to a process, a process control or any changes that could impact on the ability of the System to deliver a safe food shall trigger a review of the Food Safety Plan in addition to the annual review.  Any major changes to Food Safety Plans shall be validated and verified before implementation. 

 

2.1.3  Auditing Guidance

The auditor will seek evidence of the existence of a management review procedure at the desk audit and compliance to this requirement through a review of records and interviews with senior management and the SQF practitioner.  Evidence may include:

-  Review of the management review procedure.

-  Records  of  SQF  System  reviews  by  senior  management  and  the  depth  of  coverage  of  the  review meetings  (e.g.,  food  safety  objectives,  food  safety  measures,  customer  complaints,  test  records, product and process changes, etc.).

-  Identified actions from review meetings, and follow up on progress and outcomes of corrective actions.

-  Changes  to  the  products  and/or  operational  processes  since  the  last  audit,  and  the  extent  to  which these changes are reflected in the food safety manual.

-  The extent to which changes in materials, process or products have been validated.

-  Records of product and process changes and their validation.

 

1 Thank
In a nutshell - you review the entire SQF system once a year and show documented proof of having done so.
Thanks for the help

Similar Discussion Topics
Food Safety Culture in a Low Risk Product Facility (Wine) Flow Charts and Hazard Analysis HACCP plan for chocolate and risk area decision tree Environmental Monitoring Risk Assessment Is a scanning system required as part of the sqf certification? Distribution in Allergen Management SQF Review document Ingredient risk assesment FSSC v6 equipment management purchase specification Automatic Labeling System