Food Safety & Quality Assurance Supplier Audit...
After a contract manufacturer supplier audit one of the corrective actions said:
"The facility is currently not using Spec Deviations. If they get to a place where they need to request them, on such things as age of material, weight, etc. they will need to implement a policy around this and ensure Tyson is contacted to determine approval. No deviations requested/approved to date from Tyson"
-----------------------------------------------
I need help figuring this out!!!
Please help & thank you!
After a contract manufacturer supplier audit one of the corrective actions said:
"The facility is currently not using Spec Deviations. If they get to a place where they need to request them, on such things as age of material, weight, etc. they will need to implement a policy around this and ensure Tyson is contacted to determine approval. No deviations requested/approved to date from Tyson"
-----------------------------------------------
I need help figuring this out!!!
Please help & thank you!
Hi daveedo,
The Basic NC (the .. deviations) seems sort of self-explanative although no context is given.,
What kind of help are you seeking ?
-
Some context might be useful, eg -
Product = ?
Process = ?
FS Standard/Clause which generated the corrective action = ?
Spec Deviations with respect to ?
PS - as I understand, "Tyson" is a Food Manufacturer in USA
Dear Daveedo,
I think your deviation procedure must include the deviations related to specification of RM/PM or FG whatever.
If you do not have procedure for deviation control, you need to develop one.
This means, If any deviations such as near expiry, not stored properly, etc observed in your materials (RM/PM/FG) then you need to take formal approval from Tyson.
regards
Mahantesh
Dear Daveedo,
I think your deviation procedure must include the deviations related to specification of RM/PM or FG whatever.
If you do not have procedure for deviation control, you need to develop one.
This means, If any deviations such as near expiry, not stored properly, etc observed in your materials (RM/PM/FG) then you need to take formal approval from Tyson.
regards
Mahantesh
Agreed with Mahantesh. The supplier wants you to notify them of any deviations to your specifications. If you produce products for them and would like to have an exceptional approval (perhaps the deviation is not a hazard to the finished goods), you have to notify them in advance for their approval.
As Mahantesh stated, you need a process for deviation control and a formal release program (if not already developed).
Dear Daveedo,
I think your deviation procedure must include the deviations related to specification of RM/PM or FG whatever.
If you do not have procedure for deviation control, you need to develop one.
This means, If any deviations such as near expiry, not stored properly, etc observed in your materials (RM/PM/FG) then you need to take formal approval from Tyson.
regards
Mahantesh
Hi Mahantesh,
I guess -
RM = Raw Materials
PM = Packaging materials
but FG = ?
Hi Mahantesh,
I guess -
RM = Raw Materials
PM = Packaging materials
but FG = ?
FG= Finished Goods (Finished Product)
Thank you
FG= Finished Goods (Finished Product)
Thank you
Thank you. Maybe one of approx 94 Million according to Google. :smile:
very nice