BRC certified facility

I recently discovered while I was reviewing the R&D procedure to approve new products and control formula changes that clause 5.1.2 was not respected. Basically I found absence of compliance in the following aspects: All new products and changes to product formulation, packaging or methods of processing shall be formally approved by the HACCP team leader or authorized HACCP committee member. Many of the steps in the risk analysis process was performed by R&D personnel but not following haccp analysis. Quality staff was focused on new supplier approval and general reviewer but they have not the leadership that clause 5.1.2 requiers as main approval.

 

My question: is this finding a noncompliance one? Because the plant is certified as BRC A+ version 8.

 

Is it possible that BRC auditor minimized the impact of this finding?

 

Share this Topic
Topics you might be interested in
Internal Auditor Qualifications BRCGS Clause 8 – Production Risk Zones for Baked and Fried Snacks ASQ Certified Food Safety & Quality Auditor Handbook (4th ed.) Food Safety and Quality Auditor, Consultant Refusing a SQF trainee auditor
[Ad]
Yes to non-compliance.

Are you saying an Auditor has been in already - if that is the case, it was a miss. It happens, I'd consider it a blessing.
1 Thank

Treat your findings as an internal non-conformance and action accordingly so that you are compliant to the standard.  Auditors including BRC do sometimes miss things.

Thanks for the comments. I agree. It is likely to happen during such a big audit like BRC ones, you’ll miss something.  An ol’ auditor friend of mine used to say: “auditors are also human”.

Write yourself a nonconformance

  • decide your NC status where you feel it should be - Critical, Major, Minor,
  • correct the program and verification documents
  • follow-up on the CAPA to ensure it has been completed and is effective.

Similar Discussion Topics
Internal Auditor Qualifications BRCGS Clause 8 – Production Risk Zones for Baked and Fried Snacks ASQ Certified Food Safety & Quality Auditor Handbook (4th ed.) Food Safety and Quality Auditor, Consultant Refusing a SQF trainee auditor Roles and Responsibilities of Internal Auditor in QMS ISO 9001 2015 SQF Clause 3.6.2 – Can ISO 9001 and DOC Satisfy Supplier Approval? Auditor and CB Problems Finding for ISO22000 Clause 6.2.2 Assessment for Production Risk Zones based on Clause 4.3.1 of BRC Issue 9