Started by , Feb 08 2021 01:58 PM
2 Replies

Hi everyone we are a small usda processor. We are having a new hanging cooler installed. Where in the haccp plan does this need to be added? flow chart? reassement? Can someone help me with this Thanks

Share this Topic
Topics you might be interested in
Can one product mix different HACCP categories in the same tray? Shelf-life validation gap: HACCP says 24 months frozen, but testing only ran 4 months (beef plant) Why do you have a food safety culture plan? Cold storage and distribution HACCP hazard analysis No CCPs in a HACCP Plan - Can This Be Possible?
[Ad]

It should be added to your plant layout and also add it to your flow chart, if any specific products are stored in this cooler.

You're entire plan needs revised

 

new floor plan

new process?

new hazards?


Similar Discussion Topics
Can one product mix different HACCP categories in the same tray? Shelf-life validation gap: HACCP says 24 months frozen, but testing only ran 4 months (beef plant) Why do you have a food safety culture plan? Cold storage and distribution HACCP hazard analysis No CCPs in a HACCP Plan - Can This Be Possible? HACCP for Cannabis cultivation - no CCPs? Upgrade from HACCP to GFSI: SQF or FSSC 22000 for a juice manufacturer? Is a Separate HACCP Plan Needed for NPD Kitchen? Documenting Microbiological Hazards in HACCP Hazard Analysis - BRCGS Requirement What do you guys send when customers request a copy of HACCP plan?