What's New Unreplied Topics Membership About Us Contact Us Privacy Policy
[Ad]

Glass and breakable plastic control frequency

Started by , Aug 25 2023 09:10 AM
8 Replies
Good morning
 
 
 
I' m trying to improve our controls for glass and breakable plastic and in some of your comments I read that some of you determined the frequency of revision based on a risk analysis and I was wondering if you could give me some idea of ​​what indicators would be appropriate to use to determine the risk and with it the frequency of review.
 
 
 
I`m  currently working in a company that prints, laminates and cuts film for food packaging.
 
 
 
Thank you so much

 

 

Share this Topic
Topics you might be interested in
Mayonnaise Glass Bottling Plant Process Glass Registry BRCGS 4.9.3 Glass, brittle plastic, ceramics, and similar Glass Policy and SOP Glass and Hard plastic check
[Ad]

Greetings Ana,

 

The risk assessment a few examples are:

- the frequency of use of said equipment,

- its location, meaning if it is at a place with high traffic or frequent involvement of personnel or is it somewhere that isn't easily accesible during the processes hence it can't be knocked/ broken/ hit/ etc by activities near it,

- also, how close or far is it from the production line,

- how often is normal maintenance / replacement of breakable parts is required,

- can other maintenance procedures affect them,

- having an x-ray in good-order and properly maintained / checked also contributes to the increase of the control frequency,

- possibility of breaking or deteriorating due to high / low temperatures or vibrations of the equipment while working,

- how possible is that the personnel may detect immediately a deviation,

Hope these can get you started. However aside from the risk assessment, my personal opinion and practice is to have at least one check daily before the production starts, so as to cover the unexpected and then the rest fall under an R.A..

 

Regards!

Just an example: We had mirrors over our filling machines, but we did not fill the tank.  We use hoses to supply the machine.  We got a minor because the mirrors were not on the brittle plastic log.  If we kept them they would be a high risk that would have to be checked by the machine operators daily.  We decided to remove the mirrors altogether because we did not fill the tanks, no need to look inside.  We now only have to do the glass and brittle plastic log yearly.

Just an example: We had mirrors over our filling machines, but we did not fill the tank.  We use hoses to supply the machine.  We got a minor because the mirrors were not on the brittle plastic log.  If we kept them they would be a high risk that would have to be checked by the machine operators daily.  We decided to remove the mirrors altogether because we did not fill the tanks, no need to look inside.  We now only have to do the glass and brittle plastic log yearly.

Yearly still sounds a bit infrequent to me. What standard are you audited under?

 

I am doing glass & brittle plastic checks every week.

Last year an inspector faulted me for missing the 1" plastic gauge on the backside of a fire extinguisher.

SQF, but we are really small.  29 employees including owner.  45,000 sq ft including warehouse and all production.  We try to make all replacements with metal.

I've always done monthly audits of the full inventory, and this has sufficed in multiple companies.  But I combine that with pre-op/shift change checklists that call for operators to verify all g&bp items on their lines are intact before they begin.  Add on a check post sanitation that g&bp items are intact after cleaning, and you've successfully captured inspections of the highest risk areas at the start of every shift and post sanitation.  I also run a standalone form for reporting instances of breakage when they occur (whether it's on a line or in the middle of a room).

I do monthly as well...

 

Good morning
 
 
 
I' m trying to improve our controls for glass and breakable plastic and in some of your comments I read that some of you determined the frequency of revision based on a risk analysis and I was wondering if you could give me some idea of ​​what indicators would be appropriate to use to determine the risk and with it the frequency of review.
 
 
 
I`m  currently working in a company that prints, laminates and cuts film for food packaging.
 
 
 
Thank you so much

 

"Revision" seems to simply mean frequency of checking and its (risk) appropriateness?

 

I suggest you can modify the generic procedure attached in this post -

 

https://www.ifsqn.co...cy/#entry197516

Thank you very much to all.


Similar Discussion Topics
Mayonnaise Glass Bottling Plant Process Glass Registry BRCGS 4.9.3 Glass, brittle plastic, ceramics, and similar Glass Policy and SOP Glass and Hard plastic check Glass and Brittle Plastic Register Glass and Brittle Plastic Inventory (form) Do we need to add plastic cat trap to our Glass and Brittle Plastic controls? Reference Standards for Glass Bottle Manufacturing Glass Receptacle X-ray Validation for special-risk group population