FSSC 22000 V6 Risk-based change management process

Started by , Aug 15 2024 02:29 AM
1 Reply

Hi, 

 

Does anyone have any example or template of the new additional requirements 'risk-based change management process' for FSSC 22000 V6? 

 

I've read through the guidance document, however, I am still puzzled how to write the 'risk-based' change management process for new equipment.

 

Thanks.

Share this Topic
Topics you might be interested in
Clarifying FSSC 22000 V6 Clause 2.5.5 on Positive Testing Trends Looking for Study Materials for FSSC 22000 Version 6 Lead Auditor Exam SQF vs FSSC 22000 – Key Differences and Document Numbering Tips How to Conduct an Environmental Risk Assessment under FSSC 22000 V6.0 FSSC 22000 Additional Requirements Version 6 Section 2.5.11
[Ad]

Hi Fychan,

 

:welcome:

 

Welcome to the IFSQN forums

 

First of all, you need to assess the risk associated with new equipment and/or changes to existing equipment. The level of risk will determine the extent to which you need to manage the change.

 

For major changes such as new filling equipment it is likely that strict control of the process from purchasing, installation, commissioning, training, product trials, validation of product & shelf life and ongoing verification is required.

 

Whereas, a new pressure washer for cleaning cages in the yard will not require the same degree of scrutiny. This is what is meant by risk-based change management, it also means you focus resources on matters that are important to food safety and quality.

 

Kind regards,

 

Tony

1 Thank

Similar Discussion Topics
Clarifying FSSC 22000 V6 Clause 2.5.5 on Positive Testing Trends Looking for Study Materials for FSSC 22000 Version 6 Lead Auditor Exam SQF vs FSSC 22000 – Key Differences and Document Numbering Tips How to Conduct an Environmental Risk Assessment under FSSC 22000 V6.0 FSSC 22000 Additional Requirements Version 6 Section 2.5.11 FSSC V6 Internal Audit Checklist FSSC 22000 audit man-day calculation FSSC V6 Internal audit Checklist FSSC Lead Internal Auditor Requirements 6.1 Actions to Address risks and opportunities FSSC 22000?