What's New Unreplied Topics Membership About Us Contact Us Privacy Policy
[Ad]

Help for CA For Pitted Floor From Recent BRC

Started by , Jul 29 2013 03:04 PM
4 Replies

we had our first BRC audit last week.  Happy to say we earned a score of B.  We were given a minor for pitted floors that held water.  This is going to be a major cost for repair, that can not be completed within the time frame.  Any sugestions on how to answer the finding?  Thank you very much.

Share this Topic
Topics you might be interested in
Reusable Water Bottles on plant floor Is wearing of steel toe shoes required on the plant floor? Floor Scrubber-Floor cleaning machine Cases on floor in Cooler Storage Epoxy Floor Coatings issue
[Ad]

Hi Glendora,

 

In realation to the limited time frame, we too had to make a repair that involved some custom manufacturing an installation that would take us beyond the 28 day time frame.  After getting time and cost estimates, then placing the order for the parts needed, we conveyed this information to the auditor along with proof of payment for our custom purchase as well as a document which listed the lead times (fabrication and delivery).  We did all the standard reporting information for the NC and the auditor worked with us.  We were told that since we had provided some evidence towards correcting the NC, that this one item would be allowed to extend beyond the 28 day timeframe, but we would still have to provide evidence once it was fully complete.  I don't know if this standard practice, just our experience.  I would say once you have an approximate time frame inform the auditor of the situation.

1 Thank

Hello Glendora,

Well done on passing BRC audit at the first attempt, that's no mean feat. :clap:

 

Regards,
Simon

1 Thank

Hi Glendora,

 

In realation to the limited time frame, we too had to make a repair that involved some custom manufacturing an installation that would take us beyond the 28 day time frame.  After getting time and cost estimates, then placing the order for the parts needed, we conveyed this information to the auditor along with proof of payment for our custom purchase as well as a document which listed the lead times (fabrication and delivery).  We did all the standard reporting information for the NC and the auditor worked with us.  We were told that since we had provided some evidence towards correcting the NC, that this one item would be allowed to extend beyond the 28 day timeframe, but we would still have to provide evidence once it was fully complete.  I don't know if this standard practice, just our experience.  I would say once you have an approximate time frame inform the auditor of the situation.

Thanks for your comments.  A lot of good ideas that we can use.

Hi Glendora

If I were reviewing the response to the NC I would be asking:

a. Is there any quick temporary fix that could be put in place, and how long would it take? what is it?

b. Is there a longer term plan to permanently fix the problem and what evidence is there that it is going to be implemented?

 

The BRC accreditation process recognises that when the corrections are 'big' not everything can be put in place within 28 days.

What you then have to do is show that you have a plan to manage the problem until it can be resolved, and a plan to resolve it.

 

The plan must include timescales and evidence, (quotes, material specs, plans etc ) that show you are serious about correcting the problem.

The time scale must also be realistic, but not excessive.

If you say you will fix it but it will take 5 years, you can expect an unsympathetic response.

 

Also if the auditor returns next year and finds only the temp repair in place, or worse, nothing, you will  get your legs smacked, or the naughty chair, and a major NC.

 

rgds


Similar Discussion Topics
Reusable Water Bottles on plant floor Is wearing of steel toe shoes required on the plant floor? Floor Scrubber-Floor cleaning machine Cases on floor in Cooler Storage Epoxy Floor Coatings issue BRC 4.15.1 - Raw Material on Floor How to comply with the standard of not storing product directly on the floor? What to do with meat dropped on the floor? Usage of salt product after floor contact? Floor is not sloped to the drain getting constant overflow