Preventive Maintenance Programme

Started by , Jun 04 2014 10:44 AM
3 Replies

Hi friends,

 

My company is in process to upgrade our system from ISO22000 to FSSCH 22000. I have question on requirement of preventive maintenance stated in point 8.6 (ISO/TS 22002-1:2009. Is it necessary to have the work instruction for preventive maintenance of all machines or just enough to have the preventive maintenance checklist. Please help me :helpplease:

Share this Topic
Topics you might be interested in
Supply Chain Preventive Controls SQF Addendum - FDA Preventive Controls Audit Checklist Difference between correction, corrective action and preventive action? FSMA- Preventive Controls- Practical example of hazard analysis? Corrective and Preventive Action for lack of records caused by Absence of a Quality Manager
[Ad]

:welcome: to IFSQN Farizah.

 

I don't believe you need a full procedure for every task maintenance personnel need to do.  But it's not a bad idea to have them to ensure that everyone is performing the maintenance the same way every time.  Let's take a look at that section of code (for everyone following along this is found in the TS22002:

 

8.6 Preventive and corrective maintenance

A preventive maintenance programme shall be in place.

The preventive maintenance programme shall include all devices used to monitor and/or control food safety

hazards.

NOTE Examples of such devices include screens and filters (including air filters), magnets, metal detectors and X-ray

detectors.

Corrective maintenance shall be carried out in such a way that production on adjoining lines or equipment is not at risk of contamination

 

Maintenance requests which impact product safety shall be given priority.

 

 

 

Temporary fixes shall not put product safety at risk. A request for replacement by a permanent repair shall be

 

 

included in the maintenance schedule.

 

Lubricants and heat transfer fluids shall be food grade where there is a risk of direct or indirect contact with

the product.

The procedure for releasing maintained equipment back to production shall include clean up, sanitizing, where

specified in process sanitation procedures, and pre-use inspection.

Local area PRP requirements shall apply to maintenance areas and maintenance activities in process areas.

Maintenance personnel shall be trained in the product hazards associated with their activities.

 

 

What do you need?  You need a list of your equipment that is part of your PM program.  You need to have a temporary repair procedure.  You need to have the MSDS (and maybe a food grade statement) for all of your lubricants / heat transfer fluids that may come in contact with your product. You need an "Equipment release to production form" that has signoffs for that the equipment was cleaned up, sanitized, tools were put back, inspected.

 

It doesn't really direct that a maintenance procedure is required for each task however.

1 Thank

Hi Mr Incognita

 

Thank you very much for your opinion & helpfull information! :spoton:. Think i should go through again my procedure to ensure all the elemnt is included

 

 

hv a nice day

And you as well Farizah.  Good luck in your preparations.


Similar Discussion Topics
Supply Chain Preventive Controls SQF Addendum - FDA Preventive Controls Audit Checklist Difference between correction, corrective action and preventive action? FSMA- Preventive Controls- Practical example of hazard analysis? Corrective and Preventive Action for lack of records caused by Absence of a Quality Manager Supplier is requiring us to show our hazard analysis preventive controls for Ingredient Supply Chain Preventive Controls Program - Mycotoxins Review of preventive controls records Optical Sorting to Control Aflatoxin in Peanuts: Process Preventive Control Do you perform a root cause analysis for any type of deviations and identify preventive actions?