We are in a new build and I am new to the company and noticed that many drains were built from the reefer units, overhead across production equipment and processing areas, down into the coving at about waist height, basically small pipes running into a larger pipes (open).
I understand these have p-traps and are required by building code as they need to vent. Seeing this in both raw and RTE areas. Any suggestions on how to cover or finish these so they do not pose a food safety risk?
I’m told removal is not an option as we are, ahem, too far down the pipeline....though not sure the food authority in our area (we’ll say Canada to keep it broad) will agree. Appreciate any insight here...
I understand these have p-traps and are required by building code as they need to vent. Seeing this in both raw and RTE areas. Any suggestions on how to cover or finish these so they do not pose a food safety risk?
I’m told removal is not an option as we are, ahem, too far down the pipeline....though not sure the food authority in our area (we’ll say Canada to keep it broad) will agree. Appreciate any insight here...
11.3.9 Sanitary Facilities - Unclear on drainage
13.3.8.2 Sanitary drainage - I have a combined sewer?
The drainage in the positive pressure room and drainage system.
[Ad]
OK, those are pretty standard fixtures. You need to include them in pre op (integrity and condensation) as well as your monthly internal audit. They also need to be included in the PM program
Are you following FSEP?