ahmet

    Grade - AIFSQN

  • IFSQN Associate
  • 47 posts
  • 0 thanks
0
Neutral

Posted 22 April 2010 - 08:31 AM

How to make scheduling for oPRP's



Charles.C

    Grade - FIFSQN

  • IFSQN Moderator
  • 20,542 posts
  • 5665 thanks
1,546
Excellent

  • Earth
    Earth
  • Gender:Male
  • Interests:SF
    TV
    Movies

Posted 22 April 2010 - 01:43 PM

Dear ahmet,

I am afraid that yr question is probably too general for anyone to answer. Perhaps you could expand the information ?
If you are simply asking how to logistically select the OPRPs the first step is to follow the schedule in the standard, eg particularly starting at section 7.1. Some later more analytical steps are discussed in various places here, eg see the posts of Bennii.

Rgds / Charles.C


Kind Regards,

 

Charles.C


FSSM

    Grade - MIFSQN

  • IFSQN Member
  • 207 posts
  • 34 thanks
0
Neutral

  • Mexico
    Mexico

Posted 22 April 2010 - 05:57 PM

Dear ahmet,

I am afraid that yr question is probably too general for anyone to answer. Perhaps you could expand the information ?
If you are simply asking how to logistically select the OPRPs the first step is to follow the schedule in the standard, eg particularly starting at section 7.1. Some later more analytical steps are discussed in various places here, eg see the posts of Bennii.

Rgds / Charles.C



Maybe the question is regarding verification of OPRP´s.

Is it ahmet?

Regards,

FSSM


ahmet

    Grade - AIFSQN

  • IFSQN Associate
  • 47 posts
  • 0 thanks
0
Neutral

Posted 23 April 2010 - 07:51 AM

yes

Regards,

ahmet


Maybe the question is regarding verification of OPRP´s.

Is it ahmet?

Regards,

FSSM



FSSM

    Grade - MIFSQN

  • IFSQN Member
  • 207 posts
  • 34 thanks
0
Neutral

  • Mexico
    Mexico

Posted 23 April 2010 - 02:23 PM

yes

Regards,

ahmet




We do two audits per year, one is dedicated to check all PRP´s and OPRP´s. Our process is just warehousing food ingredients so we usually do not have to much things changing, so we just keep track of prerrequisites with monitoring activities of warehouse twice a week. But consider that you can check control measures that are more critical first, but other way, some activities might relay on other prerrequisities, so it would be a good idea to star with those first.

Regards,

FSSM