BTNashville

    Grade - Active

  • IFSQN Active
  • 4 posts
  • 0 thanks
0
Neutral

  • United States
    United States
  • Gender:Male
  • Interests:Culinary, QA, SQF, Operations

Posted 19 February 2013 - 07:26 PM

We are seeking to become SQF certified and was looking for some advise on a few things. We use an outside storage facility to store frozen raw and finished products. Would this be considered a multi site program for module 16 or would it fall under another module?


Thanks,
Brent


  • 0

Mr. Incognito

    "Mostly Harmless"

  • IFSQN Fellow
  • 1,571 posts
  • 272 thanks
131
Excellent

  • Earth
    Earth
  • Gender:Male

Posted 21 February 2013 - 06:41 PM

We are seeking to become SQF certified and was looking for some advise on a few things. We use an outside storage facility to store frozen raw and finished products. Would this be considered a multi site program for module 16 or would it fall under another module?


Thanks,
Brent


That is an excellent question and I can't say I have the best answer for you. However, I asked someone I know that has been in a similar situation and they told me that they didn't need Module 16 because they set them up as a contract service provider. The warehouse they used was inspected regularly and was not part of their SQF scope/certification other than they were set up in that aspect.

If you do not get an answer you are sure you can trust you can always talk to your CB about it I would guess.

  • 0
____________________________________________________________________________________________________

Mr. Incognito


:tardis:

Mr. Incognito is a cool frood who can travel the width and breadth of the galaxy and still know where his towel is.

SQFconsultant

    SQFconsultant

  • IFSQN Fellow
  • 5,153 posts
  • 1240 thanks
1,274
Excellent

  • United States
    United States
  • Gender:Male
  • Interests:Home now on Martha's Vineyard Island/Republic of these United States

Posted 21 February 2013 - 10:33 PM

We are seeking to become SQF certified and was looking for some advise on a few things. We use an outside storage facility to store frozen raw and finished products. Would this be considered a multi site program for module 16 or would it fall under another module?


Thanks,
Brent


It depends Brent -- you say "outside"... where exactly, as in outside, next to your main facility or outside and across town. Is this facility owned by your company, etc. If you store your finished product there prior to shipping (assuming storage and shipping are in the same location) and want/need to include this in your scope of certification you will need to add Module 16 on top of the others that you have. The questions would first need to be answered however.


Glenn Oster

http://www.GetGoc.com

  • 0

All the Best,

 

All Rights Reserved,

Without Prejudice,

Glenn Oster.

 

 

Glenn Oster Consulting, LLC 

SQF Consultant

http://www.GlennOster.com  -- 774.563.6161

 

 

Blog

https://t.me/gcemvi

 

 

 

 

 

 

 

 


BTNashville

    Grade - Active

  • IFSQN Active
  • 4 posts
  • 0 thanks
0
Neutral

  • United States
    United States
  • Gender:Male
  • Interests:Culinary, QA, SQF, Operations

Posted 22 February 2013 - 01:11 PM

Sorry should've been more descriptive. The storage facility is a county over and we don't own them. Its a service we pay for, but do ship finished product from this facility.


Thanks,
Brent


  • 0

SQFconsultant

    SQFconsultant

  • IFSQN Fellow
  • 5,153 posts
  • 1240 thanks
1,274
Excellent

  • United States
    United States
  • Gender:Male
  • Interests:Home now on Martha's Vineyard Island/Republic of these United States

Posted 22 February 2013 - 10:40 PM

Sorry should've been more descriptive. The storage facility is a county over and we don't own them. Its a service we pay for, but do ship finished product from this facility.


Thanks,
Brent


In that case there is no reason for you to have the additional module.



Glenn Oster

http://www.GetGoc.com

  • 0

All the Best,

 

All Rights Reserved,

Without Prejudice,

Glenn Oster.

 

 

Glenn Oster Consulting, LLC 

SQF Consultant

http://www.GlennOster.com  -- 774.563.6161

 

 