The scenario here is a dry Organic Soy Protein powder that is being processed. The shift has ended and being that they are going to run the same product first thing in the morning (which is 12 hours away) they want to just cover the machinery up and then just rinse the equipment off in the morning (without any Swab testing) and start production again.
Per our current SOP's, the time of 12 hours says wash, rinse, spray Organic solution, wait 10 minutes dry time, Swab test - good - proceed, fail - re-clean and retest.
I am wondering if anyone else out there is doing ATP testing and what time parameters do they have in place. Are mine to stringent or? Again, we are a dry product facility and do not spray wash our rooms down but rather use the three bucket process.