Hello Al,
Does anyone can provide an example of Emergency Supplier Approval Program to comply with FSSC 22000 (or SQF or BRC)?
Thanks in advance.
O.C
Posted 12 March 2020 - 10:29 PM
Hello Al,
Does anyone can provide an example of Emergency Supplier Approval Program to comply with FSSC 22000 (or SQF or BRC)?
Thanks in advance.
O.C
Posted 12 March 2020 - 10:59 PM
This is my stripped down take on emergency supplier approval:
1. If they provide a current GFSI-recognized Certificate then they are immediately approved. Then they have 48 hours to send a COA from an independent laboratory after the material has shipped.
2. If they don't have current GFSI-recognized Certificate, then they have to provide the COA from an independent laboratory before purchasing.
Thanked by 1 Member:
|
|
Posted 13 March 2020 - 11:42 AM
Hi mate,
First of all i would like to suggest you to approve more than one supplier for particular material (raw / packaging material etc.).
In case of emergency purchase
A. Search the suppliers who are certified with any GFSI scheme (BRC, BRC IoP, FSSC, SQF, IFS). Along with the certificate, you must ask for the CoA and the same material shall be tested to verify whether it is complied with you organization's set specification.
B. If you dont have the facility for 100% testing of the product, you must ask the supplier for third party inspection of the particular product. in that case you just verify that the lab is IS 17025 certified or not.
C. Try to choose supplier located near to your organization, so that personnel from QA or QC team can visit the location of supplier to verify whether the safe practices being followed (This must be performed when the supplier is not certified with any of the GFSI Scheme). In this case you must use a checklist which required information as per the requirement of FSSC/BRC etc.
This is the only thing you can do in case of emergency purchase
Further information if any highly appreciable
regards
Bhupendra Sharma
Posted 13 March 2020 - 02:58 PM
Hi O.C,
this is what i have in my supplier approval SOP:
"In cases where evaluation of a supplier of raw materials or packaging has to be done quickly (e.g. urgent order), only the following will be looked at:
If the manufacturer is GFSI approved, do not deal with GMO or irradiated materials, purchase order can be placed, and full evaluation process can be carried out afterwards.
In all other cases, the full supplier approval process shall be carried out."
that was enough for both FSSC22000 & BRC.
Aurélie
Posted 13 March 2020 - 08:30 PM
Hello,
Thanks all for the inputs. Here is the preliminary version of this procedure for ingredients/raw materials:
Thanked by 1 Member:
|
|
Posted 13 March 2020 - 09:41 PM
Hello All,
Does anyone can provide an example of Emergency Supplier Approval Program to comply with FSSC 22000 (or SQF or BRC)?
Thanks in advance.
O.C
Hi OC,
This topic is considered in both SQF and BRC, eg -
SQF8
2.4.4.2 The receipt of raw materials, ingredients, and packaging materials received from non-approved suppliers shall be acceptable only in an emergency situation, and provided they are inspected or analyzed before use.
Guidance -
The receipt of raw materials from non-approved suppliers is acceptable, but only in an emergency situation, and provided the materials are inspected before use. Records of the use of non-approved suppliers and their inspections shall be maintained.
---------------------------------------------------------
BRC8
3.5.1.7 The procedures shall define how exceptions to the supplier approval processes in clause 3.5.1.2 are handled (e.g. where raw material suppliers are prescribed by a customer) or where information for effective supplier approval is not available (e.g. bulk agricultural commodity products) and instead product testing is used to verify product quality and safety.
When a site produces customer-branded product, the customer shall be made aware of the relevant exceptions.
Guidance involves addressing requirements such as -
(i) risk assessment of the product itself and potential impact on related products (ii) "100%" material inspection, (iii) Certificates of Analysis, (iv) increased microbiological sampling, (v) reviewed third party report, (vi) documented agreed specifications.
Kind Regards,
Charles.C