Posted 18 July 2023 - 02:36 PM

Hi

According to BRC issue 9, any new equipment must have :

  • Equipment Specification Check list
  • Equipment/Machinery Movement/Commissioning Sheet

After implementing BRC issue 9 no equipment was purchased. Is it necessary to fill these forms for old equipment those are in production?



Bansal

    Grade - MIFSQN

  • IFSQN Member
  • 82 posts
  • 16 thanks
14
Good

  • Canada
    Canada

Posted 18 July 2023 - 03:18 PM

Hi,
No, you need not to do it for old equipment.
Once you update it in your procedure, start doing it for new incoming equipment's.

Hope it helps!
Thanks



Fishlady

    Grade - MIFSQN

  • IFSQN Member
  • 210 posts
  • 54 thanks
26
Excellent

  • United States
    United States
  • Gender:Female

Posted 28 July 2023 - 02:29 PM

The BRC Interpretation Guide specifically states that the requirement only applies to "new" equipment- meaning equipment newly purchased (whether brand-new or new-to-you) or significantly modified.