We have a BRC Audit on Thursday. Audit was scheduled before I joined the company.
We are not yet running any product. We're still in construction mode. Moving in equipment, building walls, installing lines. etc.
I have MOST of our policies in place. Still waiting for them to get approved from out Canadian office.
I don't have any HACCP plans yet, as lines aren't completely in place yet. I do have a pretty good start on a couple of our lines that will be running later, as they are the same as our CA facility. But what we're starting with isn't ran up there.
I don't even have any QA test equipment yet (MOST of it has been ordered)
They were hoping to be production before now, which is why the audit was scheduled. But now we're looking at a couple test runs in April.
What should I except during this audit? I think it should be postponed until we're close to production, but it's not my call.