Hi
I have developed and implemented Registers or preventative and planned maintenance. Would like some help in writing a procedure for conducting the maintenance.
Regards
Humaid Khan
Posted 03 February 2016 - 11:35 PM
Hi
I have developed and implemented Registers or preventative and planned maintenance. Would like some help in writing a procedure for conducting the maintenance.
Regards
Humaid Khan
Posted 04 February 2016 - 04:30 PM
Some basic elements I put in place for both preventative maintenance and for urgent repairs:
-whether the work poses a contamination risk to the area on which work is done or to adjacent areas (protect the area as needed)
-follow chemical and lubricant policy and use only approved materials
-guidelines for temporary repair (no duct tape, cloth ties, material that can cause or harbor contamination, etc.)
-tool and material accountability
-whether or not the equipment requires cleaning following the work (trained person completes the cleaning step with approved cleaners/sanitizers)
-inspection of the area and equipment following work (no wires left on the floor, no nuts/bolts, tools left out, etc) - QA and maint personnel complete inspection
-positive release of the area/equipment following inspection
Posted 04 February 2016 - 05:58 PM
Some basic elements I put in place for both preventative maintenance and for urgent repairs:
-whether the work poses a contamination risk to the area on which work is done or to adjacent areas (protect the area as needed)
-follow chemical and lubricant policy and use only approved materials
-guidelines for temporary repair (no duct tape, cloth ties, material that can cause or harbor contamination, etc.)
-tool and material accountability
-whether or not the equipment requires cleaning following the work (trained person completes the cleaning step with approved cleaners/sanitizers)
-inspection of the area and equipment following work (no wires left on the floor, no nuts/bolts, tools left out, etc) - QA and maint personnel complete inspection
-positive release of the area/equipment following inspection
Hi RMAV,
thks for above.
Is this a generic menu or specifically targeted for bakeries ?.
Not my area but based on some recent posts, i would have added to maintain a vigilance for aluminium shavings due degrad(ed)ing tray/shelving alignments.
Kind Regards,
Charles.C
Posted 04 February 2016 - 06:41 PM
Apologies, Charles.C, I usually add a disclaimer. I provided a generic list of what I look for but I don't have experience in Bakery or BRC.
That's a good point with the shavings. Something to watch for in preventative maintenance or repairs is will there be any cutting, drilling, filing, etc., where will the work occur, etc...
Posted 04 February 2016 - 07:02 PM
Hi RMAV,
No problem, I was just curious. The more, the merrier.
I agree that many of the necessities are undoubtedly groupable.
Kind Regards,
Charles.C
Global Food Safety Standards →
BRCGS - Food Safety →
BRC Requirements for ExportStarted by LGreen, 12 Feb 2025 ![]() |
|
![]() |
|
Global Food Safety Standards →
BRCGS - Food Safety →
BRC Standard 3.4.1Started by blissdairycow, 06 Jan 2025 ![]() |
|
![]() |
|
Global Food Safety Standards →
BRCGS - Food Safety →
Electronic Maintenance Records for BRCGS ComplianceStarted by Diana Jarczok-Stec, 18 Nov 2024 ![]() |
|
![]() |
|
Global Food Safety Standards →
BRCGS - Food Safety →
BRCGS 4.6.4 V9 - Static Equipment Replacement: Food Safety ImplicationsStarted by jbaus, 06 Nov 2024 ![]() |
|
![]() |
|
Global Food Safety Standards →
BRCGS - Packaging Materials →
BRCGS Packaging Materials Issue 7 - Launch webinar 28th October 2024Started by Tony-C, 29 Sep 2024 ![]() |
|
![]() |
0 members, 0 guests, 0 anonymous users