Hi
I have developed and implemented Registers or preventative and planned maintenance. Would like some help in writing a procedure for conducting the maintenance.
Regards
Humaid Khan
Posted 03 February 2016 - 11:35 PM
Hi
I have developed and implemented Registers or preventative and planned maintenance. Would like some help in writing a procedure for conducting the maintenance.
Regards
Humaid Khan
Posted 04 February 2016 - 04:30 PM
Some basic elements I put in place for both preventative maintenance and for urgent repairs:
-whether the work poses a contamination risk to the area on which work is done or to adjacent areas (protect the area as needed)
-follow chemical and lubricant policy and use only approved materials
-guidelines for temporary repair (no duct tape, cloth ties, material that can cause or harbor contamination, etc.)
-tool and material accountability
-whether or not the equipment requires cleaning following the work (trained person completes the cleaning step with approved cleaners/sanitizers)
-inspection of the area and equipment following work (no wires left on the floor, no nuts/bolts, tools left out, etc) - QA and maint personnel complete inspection
-positive release of the area/equipment following inspection
Posted 04 February 2016 - 05:58 PM
Some basic elements I put in place for both preventative maintenance and for urgent repairs:
-whether the work poses a contamination risk to the area on which work is done or to adjacent areas (protect the area as needed)
-follow chemical and lubricant policy and use only approved materials
-guidelines for temporary repair (no duct tape, cloth ties, material that can cause or harbor contamination, etc.)
-tool and material accountability
-whether or not the equipment requires cleaning following the work (trained person completes the cleaning step with approved cleaners/sanitizers)
-inspection of the area and equipment following work (no wires left on the floor, no nuts/bolts, tools left out, etc) - QA and maint personnel complete inspection
-positive release of the area/equipment following inspection
Hi RMAV,
thks for above.
Is this a generic menu or specifically targeted for bakeries ?.
Not my area but based on some recent posts, i would have added to maintain a vigilance for aluminium shavings due degrad(ed)ing tray/shelving alignments.
Kind Regards,
Charles.C
Posted 04 February 2016 - 06:41 PM
Apologies, Charles.C, I usually add a disclaimer. I provided a generic list of what I look for but I don't have experience in Bakery or BRC.
That's a good point with the shavings. Something to watch for in preventative maintenance or repairs is will there be any cutting, drilling, filing, etc., where will the work occur, etc...
Posted 04 February 2016 - 07:02 PM
Hi RMAV,
No problem, I was just curious. The more, the merrier.
I agree that many of the necessities are undoubtedly groupable.
Kind Regards,
Charles.C
Global Food Safety Standards →
BRCGS - Food Safety →
Calibration Certificate ExpirationStarted by Benty666, 05 Mar 2024 BRC, BRCGS, CCP |
|
||
Global Food Safety Standards →
BRCGS - Food Safety →
ISO 8573-1 Compliance-Point of UseStarted by CoffeeCan, 26 Feb 2024 ISO, BRCGS, BRC, ISO 8573-1, POU and 2 more... |
|
||
Food Safety Topics →
Documentation & Document Control →
Controlled Documents ListStarted by chrisolson, 17 Jan 2024 BRC, controlled doc, doc dates and 1 more... |
|
||
Global Food Safety Standards →
BRCGS - Food Safety →
BRC risk zone clarificationStarted by souswes, 04 Jan 2024 brc, seafood, procesing and 1 more... |
|
||
Answered
Global Food Safety Standards →
BRCGS - Food Safety →
BRCGS - Control of personal medicineStarted by INL, 09 Nov 2023 BRC, personal medication, control |
|
0 members, 0 guests, 0 anonymous users